You are here

Plans and projects

Works are now underway to upgrade and repair Kerferd Road Pier which has been closed to the public since November 2017.

Kerferd Road Pier is a popular spot for recreational boating, fishing and sightseeing. These works will ensure the local heritage and character of the pier remains an important feature in the Albert Park Foreshore.

To reinstate the structural integrity of the pier, major repairs to Kerferd Road Pier will include:

- Replacing broken piles
- Building a new deck
- Repairs of the crossheads and beams

Parks Victoria has engaged contractors, Simpson Construction Pty Ltd, to undertake the $1.6 million program of works.

Subject to weather conditions, the works are expected to be completed by the end of April 2019.

The historical Kerferd Road Pier has long been a popular destination along the Albert Park Foreshore for fishing, boating and recreational pier-goers.

We will continue to keep the community updated as works progress.