Lake Natimuk Weir Replacement
Project status
- This project is set to commence in early April 2024, with works being completed in May.
- SKR Demolition and Earthmoving Pty Ltd has been engaged to deliver the agreed works.
Last updated: March 2024
The project
This project will complete a partially constructed concrete weir at Lake Natimuk.
Works on a new weir structure had been commenced in 2016 by the Natimuk Lake Foreshore Committee of Management. This project will complete and improve the stability of the weir, establish embankments and ensure the water level of the lake is managed appropriately.
As part of the project, the original earthen and timber weir will also be removed.
The project follows extensive consultation with the local community and stakeholders. It has also been guided by a Wimmera Catchment Management Authority-commissioned Ecological Impact Report, which included assessments to identify the biological values at Lake Natimuk and the connecting Natimuk Creek.
Located in western Victoria, the network of wetlands around Natimuk has immense environmental significance as a habitat for birds, particularly waders. Like many lakes in Australia, Lake Natimuk is ephemeral, naturally cycling through periods of being dry, periods of shallow water levels and periods of higher, deeper water levels.
Project benefits
This project will ensure the water level within the lake is managed appropriately. Water retained in the lake currently provides significant benefits to environmental values and recreational opportunities.
Project timeline
Subject to on-ground conditions, works are expected to commence in early April 2024 and be completed in May.
Project funding
This project is being delivered as part of the Asset Regeneration Program, a $24.76 million investment by the Victorian Government to remove unsafe infrastructure and to repair or replace assets across the Parks Victoria estate.
Environment and cultural heritage management
This project is being guided by environmental and cultural heritage planning and assessments.
This includes the Lake Natimuk Weir Modification Ecological Impact Report in 2018, and a Working on Waterways Permit.
A Cultural Heritage Permit has been approved for these works, with conditions including that site supervisors will be onsite during excavations to ensure no impacts to cultural values.
Who are we working with?
This project is being delivered with support from the Barengi Gadjin Land Council.
We’ve also been working with the Natimuk Lake Foreshore Committee of Management, Horsham Rural City Council and the Wimmera Catchment Management Authority.